The final estimated cost of the redevelopment of Gerrards Cross police station has increased by more than £2million.
The initial build cost estimated in 2016 was £5.3 million, however following detailed site investigations and design work the development is expected to cost £7.8 million.
Original overall costs were later estimated by a contractor to be £8.5 million – however this figure was reduced based on the assumption savings would be made through a number of design efficiencies.
A detailed business case will be presented to SBDC’s cabinet before construction begins – subject to planning permission.
To view the council report on the development of the site visit http://sbdc-spider2.southbucks.gov.uk/democracy/documents/s30707/Cabinet%2017.04.18%20Redevelopmento%20Gerrard%20X%20Police%20Stn%20site.pdf
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel