During the course of next week, Transport for Buckinghamshire will be carrying out work in the following places as part of the Strategic Highway Maintenance Programme. As some activities depend on the weather, dates can change at short notice.

A413 Amersham Bypass, Amersham – whole length (Monday 1 July to Wednesday 3 July)

Conventional surfacing works taking place using a night time road closure between 7pm to 6am.

Penmoor Close, Sands - whole length (Monday 1 July)

Surface dressing preparatory patching works taking place using a day time road closure between 7:00am to 7:00pm

Swan Lane, The Lee - Chesham Lane to Jenkins Lane (Tuesday 2 July to Wednesday 10 July)

Surface dressing preparatory patching works taking place using a day time road closure between 7:00am to 7:00pm

Langley Park Road, Iver – Cecil Road to Hollybush Lane (Thursday 4 July to Monday 15 July) **weekend working**

Conventional surfacing works taking place using a night time road closure between 7pm to 6am each week night and a 24 hrs closure in place over the weekend of the 6 and 7 July to carry out resurfacing of the roundabout at the junction of Wood Lane.

Highland Road, Amersham - Stanley Hill Avenue to Hyrons Lane (Monday 1 July to Tuesday 2 July)

Micro-surfacing preparatory patching works taking place using a day time road closure between 7am and 7pm

Stanley Hill Avenue, Amersham - Stanley Hill to Hazel Park (Monday 1 July to Tuesday 2 July)

Micro-surfacing preparatory patching works taking place using a day time road closure between 7am and 7pm

Cressex Road, High Wycombe - A4010 to Marlow Road (Monday 1 July to Thursday 4 July)

Micro-surfacing preparatory patching works taking place using a day time road closure between 7am and 7pm

Dukes Wood Avenue, Gerrards Cross - Dukes Wood Avenue to A40 (Wednesday 3 July to Friday 5 July)

Micro-surfacing preparatory patching works taking place using a day time road closure between 7am and 7pm

Meare Estate Roads, Wooburn Green - A4094 to A4094 (Monday 1 July)

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Heath Road, Beaconsfield - Holtspur Top Lane to end (Monday 1 July to Thursday 4 July)

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Wood Way, Beaconsfield - Heath Road to end (Monday 1 July to Thursday 4 July)

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

East Way, Beaconsfield - Heath Road to end (Monday 1 July to Thursday 4 July)

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

South Way, Beaconsfield - Heath Road to end (Monday 1 July to Thursday 4 July)

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Long View, Beaconsfield - Heath Road to end ( Monday 1 July to Thursday 4 July)

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Buckingham Drive, High Wycombe - Micklefield Road to end (Thursday 4 July to Saturday 6 July) **weekend working**

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Buckingham Close, High Wycombe - Buckingham Drive to end (Thursday 4 July to Saturday 6 July) **weekend working**

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Farm Close, High Wycombe - Winslow Gardens to end (Thursday 4 July to Saturday 6 July) **weekend working**

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Tilling Crescent, High Wycombe - Buckingham Drive to Buckingham Drive (Thursday 4 July to Saturday 6 July) **weekend working**

Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm

Chapel Road, Ford (near Aylesbury) - Bridge over the Meadle Brook - Bridge over the Meadle Brook (Monday 1 July to Friday 5 July)

Bridge wing wall reconstruction using local traffic management between 7:30am and 6:00pm

Chapel Lane, High Wycombe - Gallows Lane junction - Toweridge Lane junction (Monday 1 July to Friday 5 July)

Major maintenance to concrete retaining wall using two way traffic signals between 9:30am and 3:30pm

Drainage works

West Lane, Bledlow - Near to Bakehouse Farm (Monday 1 July to Wednesday 10 July)

Drainage improvement works using a daytime road closure between 8am and 5pm