During the course of the coming week, Transport for Buckinghamshire will be carrying out work in the following places as part of the Strategic Highway Maintenance Programme.
As some activities depend on the weather, dates can change at short notice.
During this busy period, weekend working may take place in some places as indicated in the dates below.
Carriageway surfacing
Langley Park Road, Iver – Mansion Lane to Cecil Road (Monday 15 July to Tuesday 16 July)
Conventional surfacing works taking place using a night time road closure between 7pm to 6am
A418 Aylesbury Road, Haddenham – Low Lane to Haddenham Crossroads (Wednesday 17 July to Thursday 25 July)
Conventional surfacing works taking place using a night time road closure between 7pm to 6am
Chartridge Lane, Chesham - Westdean Lane to Penn Avenue (Monday 15 July to Wednesday 17 July)
Micro-surfacing preparatory patching works taking place using a road closure in operation between 9:30am and 3pm
Stonecroft Avenue, Iver - Langley Park Road to end (Monday 15 July to Tuesday 16 July)
Micro-surfacing preparatory patching works taking place using a day time road closure between 7:30am and 4pm
Glaisyer Way, Iver - Warren Field to Alder Way (Wednesday 17 July to Thursday 18 July)
Micro-surfacing preparatory patching works taking place using a day time road closure between 8:00am and 5:00pm
Hobart Road, High Wycombe - Adelaide Road to Kingston Road (Monday 15 July to Tuesday 16 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Hobart Close, High Wycombe - Kingston Road to end (Monday 15 July to Tuesday 16 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Sussex Close, High Wycombe - Salisbury Road to end (Monday 15 July to Tuesday 16 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Salisbury Road, High Wycombe - Hobart Road to Kingston Road (Monday 15 July to Tuesday 16 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Eastern Dene, Hazlemere - Holmer Green Road to A404 (Tuesday 16 July to Wednesday 17 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Kingshill Road, High Wycombe - A404 to Green Road (Thursday 18 July)
Micro-surfacing remedial works taking place using a day time road closure between 9:30am and 4:30pm
Coningsby Road, High Wycombe - Green Hill to Hamilton Road (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Coates Lane, Downley - Hughenden Boulevard to Littleworth Road (Friday 19 July to Saturday 20 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Main Road, Naphill - Valley Road to Stocking Lane (Saturday 20 July)
Micro-surfacing works taking place using a day time road closure between 9:30am and 3:30pm
Portway Drive, High Wycombe - A40 to end (Saturday 20 July to Sunday 21 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Manor Crescent, Wendover - Manor Road to Manor Road (Tuesday 16 July to Wednesday 17 July)
Micro-surfacing works taking place using a day time road closure between 9:30am and 3pm
Woodfield, Lacey Green - Main Road to end (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Greenlands, Lacey Green - Main Road to end (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Westlands Road, Lacey Green - Main Road to end (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Meadow Rise, Lacey Green – Main Road to End (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Roundlands, Lacey Green - Main Road to end (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Eastlands, Lacey Green – Roundlands to end (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Goodacres Lane, Lacey Green - Main Road to end (Thursday 18 July to Friday 19 July)
Micro-surfacing works taking place using a day time road closure between 8:00am and 5:00pm
Waborne Road, Bourne End - Blind Lane to Evenlode Road (Thursday 18 July to Friday 19 July)
Ironwork adjustment works taking place using a localised traffic management between 8:00am and 5:00pm
Evenlode Road, Bourne End - Roman Way to Waborne Road (Friday 19 July to Saturday 20 July)
Ironwork adjustment works taking place using a localised traffic management between 8:00am and 5:00pm
Roman Way, Bourne End - Waborne Road to Loddon Road (Saturday 20 July to Monday 22 July)
Ironwork adjustment works taking place using a localised traffic management between 8:00am and 5:00pm
Drain maintenance
Aylesbury Road and Peters Lane, Monks Risborough - Chestnut Close to Mill Lane and Aylesbury Road to Westfields (Monday 8 July to Wednesday 17 July)
Drainage works taking place using 2 and 3 way traffic lights in operation between 9.30 am and 3.30pm
Safety barrier maintenance
Slough Rd, A355 & A40 London Road, Beaconsfield - Slough Rd A355 - A40 London Rd - including roundabout (8 July to 16 July)
Safety barrier works taking place using lane closures in operation between 9.30am and 3.30pm.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel