This is where Transport for Bucks will be working throughout the week. 

As some activities depend on the weather, dates can change at short notice.

Weekend working is planned only in those places indicated.

Carriageway surfacing schemes

A413 Wendover Bypass – London Road roundabout to Nash Lee Road roundabout (Thursday 10 October to Sunday 13 October) ** weekend working** - Conventional carriageway surfacing works using a night time road closure in operation between 7pm and 6am with a 24 hr closure in operation over the weekend of the 12 and 13 of October.

Marlow Road, Bourne End – west of Sheepridge Lane to Blyton House (Monday 7 October to Friday 11 October). Conventional carriageway surfacing works using a night time road closure in operation between 7pm and 6am

A41 Aylesbury Road, Aston Clinton - various locations along length of road (Monday 7 October to Wednesday 9 October). Joint sealing works using a night time road closure in operation between 7pm and 6am

A40 Abbey Way Gyratory, High Wycombe - various locations along length of road (Thursday 10 October). Joint sealing works using a night time road closure in operation between 7pm and 6am

A4128 Hughenden Road, High Wycombe - various locations along length of road (Friday 11 October). Joint sealing works using a night time road closure in operation between 7pm and 6am

A4128 Valley Road, Cryers Hill - various locations along length of road (Friday 11 October). Joint sealing works using a night time road closure in operation between 7pm and 6am

Heath Way, Iver – Bangors Road North to end (Monday 7 October). Ironwork adjustments for micro-surfacing using local traffic management in operation between 8am and 5pm

Coningsby Road, High Wycombe - whole length (Monday 7 October to Thursday 10 October). Ironwork adjustments for micro-surfacing using local traffic management in operation between 8am and 5pm

Laurels Road, Iver - Heath Way to end (Tuesday 8 October). Ironwork adjustments for micro-surfacing using local traffic management in operation between 8am and 5pm

Langley Park Road, Iver - Mansion Lane to Cecil Road (Wednesday 9 October to Friday 11 October). Ironwork adjustments for micro-surfacing using 2 way traffic lights in operation between 9:30am and 3:30pm

Clayhill, Booker - Clay Lane to end (Saturday 12 October to Monday 14 October) **weekend working** Ironwork adjustments for micro-surfacing using local traffic management in operation between 8am and 5pm

Eastern Dene, Hazlemere - A404 to Holmer Green Road (Saturday 12 October to Wednesday 16 October) **weekend working** Ironwork adjustments for micro-surfacing using local traffic management in operation between 8am and 5pm

Chartridge Lane, Chesham - outside no 385  to outside no 325 (Monday 7 October to Wednesday 9th October). Kerbing and drainage works for micro-surfacing  using two way traffic lights between 9.30am and 3.30pm 

Footway repairs

Beaconsfield Road & Rosebery Road, Aston Clinton - entire roads (Monday 7 October to Friday 4  October). Footway resurfacing using local traffic management in operation between 7am to 7pm

Desborough Avenue, High Wycombe - Carver Hill Road to Suffield Road (Monday 7 October to Tuesday 12 November). Footway resurfacing using 2 way signals traffic management between 9:30am to 3:30pm

Drainage work       

Newbarn Lane, Seer Green -  junction with Rawlings Lane (Monday 7 October to Wednesday 9 October). Drainage improvement works using temporary traffic lights in operation between 9.30am and 3.30pm

Thorney Lane South, Iver - near to the industrial estate (Monday 7 October to Monday 7 October). Drainage improvement works using temporary traffic lights in operation between 9.30am and 3.30pm

Amersham Road - junction with Willow Chase, Hazlemere (Tuesday 8 October to 9 October). Drainage improvement works using temporary traffic lights in operation between 9.30am and 3.30pm