This is where Transport for Bucks will be carrying out roadworks this week. 

No weekend working is scheduled.

Surface Dressing Programme

Hammersley Lane, Tylers Green - various locations along length of road (Monday 1 March to Tuesday 2 March). Preparatory patching works using a daytime road closure in operation between 9:30am and 4:30pm.

Ferry Lane, Bourne End - various locations along length of road (Thursday 4 March to Friday 5 March). Preparatory patching works using a night-time road closure in operation between 7:30pm and 6:00am.

Welders Lane, Jordans - Jordans Lane to Grove Lane (Monday 1 March to Tuesday 2 March). Preparatory patching works using a daytime road closure in operation between 7:30am and 4:30pm.

Love Green Lane, Iver - various locations along length of road (Thursday 4 March to Monday 8 March). Preparatory patching works using a daytime road closure in operation between 7:30am and 4:30pm.

Plane and Patch Programme

Leighton Road, Wingrave - Wingrave Village to Mentmore Crossroads (Monday 1 March to Wednesday 3 March). Patching works using a daytime road closure in operation between 7:30am and 5:30pm.

Bangors Road South, Iver - A4007 to the B470 (Monday 1 March to Wednesday 3 March). Patching works using a daytime road closure in operation between 7:30am and 4:30pm.

Ledburn Road, Ledburn - Mentmore Crossroads to the B488 junction (Thursday 4 March to Tuesday 9 March). Patching works using a daytime road closure in operation between 7:30am and 5:30pm.

Bellfield Road, High Wycombe - various locations along length of road (Wednesday 3 March). Patching works using a daytime road closure in operation between 7:30am and 5:30pm.

Chesham Road, Amersham - various locations along length of road (Thursday 4 March to Friday 5 March). Patching works using a daytime road closure in operation between 9:30am and 3:30pm.

Dropmore Road, Burnham - various locations along length of road (Wednesday 3 March). Patching works using a daytime road closure in operation between 7:30am and 4:30pm.

Footway Structural Repair Programme

Wendover Road, Aylesbury - Camborne Avenue to Eascote Road (Monday 1 March to Friday 12 March. Footway reconstruction works using a footway closure and lane controls in operation between 7:30am and 5:30pm.

Desborough Avenue, High Wycombe - length of footways (Monday 1 March to Monday 5 April). Footway reconstruction works using footway closures and temporary traffic signals in operation between 7:30am and 5:30pm.

Kendalls Close, High Wycombe - whole length of footway (Tuesday 2 March to Friday 5 March). Footway improvement works using a footway closure in operation between 7:30am and 5:30pm.

Drainage Improvement Schemes

North End Road, Steeple Claydon - various locations (Monday 1 March to Friday 12 March). Drainage improvement works using localised traffic management in operation between 9:00am and 4:00pm.