This is where Transport for Bucks teams will be working this week. 

Plane and Patch Programme:

  • Witheridge Lane, Penn – From Pauls Hill to Clay Street (Monday 4 April to Wednesday 27 April). Surface patching works using two- and three-way temporary traffic lights in operation Monday to Friday between 9:30am and 3.30pm.
  • Oaklington Avenue, Little Chalfont – From Amersham Way to Church Grove (Wednesday 20 April to Monday 25 April). Surface patching works using a road closure in operation Monday to Friday between 9:30am and 3:30pm.
  • Alderbourne Lane, Fulmer – From Fulmer Road to Huntswood Lane (Monday 25 April to Thursday 28 April). Surface patching works using a road closure in operation Monday to Friday between 9am and 3pm.
  • Aston Abbotts Road, Aston Abbotts – From Wing Road to High Street (Thursday 28 April to Thursday 12 May). Surface patching works using a road closure in operation Monday to Friday between 8am and 4pm.

Drainage Improvement Schemes:

  • West End Lane, Weston Turville – Whole of West End Lane (Monday 19 April to Friday 27 May). Drainage improvement works using give and take traffic management in operation Monday to Friday between 8am and 5pm.
  • Hog Lane, Ashley Green – The junction with Johns Lane (Monday 25 April to Friday 6 May). Drainage improvement works using a road closure in operation Monday to Friday between 8am and 5pm.

Footway Improvement Schemes: 

  • White Hill, Chesham – From Kirtle Road to White Hill Close (Tuesday 19 April to Sunday 1 June). Footway improvement works using 2-way temporary traffic lights in operation Monday to Sunday 9:30am and 3:30pm.
  • Springfields, Padbury – Adjacent to the A413 (Monday 4 April to Friday 13 May). Footway improvement works using a footway give and take management system in operation Monday to Friday, 7am to 7pm.

Network Improvement Schemes:

  • A4010 Risborough Road, Stoke Mandeville – Junction of Lower Road and Station Road (Monday 28 March to Friday 29 April). Pedestrian crossing improvement works using 3-way temporary traffic lights and lane restrictions in operation between 9:30am and 3:30pm.
  • A413 Amersham Road, Gerrards Cross – Junction of Chalfont Park to Dual Carriageway (Tuesday 19 April to Tuesday 26 April). Undertaking works to close the gap, effectively creating a no right turn, to the central reservation on the A413 Amersham Road, Gerrards Cross using a lane closure in operation Monday to Friday between 9:30am – 3:30pm.

Street Lighting Schemes:

  • Elmhurst Close, High Wycombe – Outside No. 26 (Tuesday 26 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Green Hill, High Wycombe – Junction with Green Road (Tuesday 26 April). Lamp column replacement works using 3-way temporary traffic lights as traffic management in operation between 9:30am and 3:30pm.
  • Green Road, High Wycombe – Outside No. 11 (Tuesday 26 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Hardenwaye, High Wycombe – Adjacent to No. 2 (Tuesday 26 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Herbert Road, High Wycombe – Outside No. 119 (Tuesday 26 April). Lamp column replacement works using 4-way temporary traffic lights as traffic management in operation between 8am and 5pm.
  • Chearsley Road, Long Crendon – From Needlemakers to Pinners Way (Tuesday 26 April to Friday 29 April). Lamp column replacements works using 2-way temporary traffic lights as traffic management in operation between 9:30am and 3:30pm.
  • Huntley Close, High Wycombe – Behind No. 11 Brands Hill Avenue (Wednesday 27 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Micklefield Road, High Wycombe – Outside No. 385 (Wednesday 27 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Rushbrooke Close, High Wycombe – Outside No. 40 & Sub-Station (Wednesday 27 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • The Quadrant, High Wycombe – Outside No. 9 (Wednesday 27 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Totteridge Drive, High Wycombe – Outside No. 1 & 10 (Thursday 28 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Totteridge Lane, High Wycombe – Outside No. 113 (Thursday 28 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Tyzack Road, High Wycombe – Outside No. 86 (Friday 29 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Walton Drive, High Wycombe – Outside No. 33 (Friday 29 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.
  • Wellesbourne Gardens, High Wycombe – Junction with Tower Street & Adjacent to No. 8 (Friday 29 April). Lamp column replacement works using give and take traffic management in operation between 8am and 5pm.

Bridge Schemes:

  • High Street, Marlow – Marlow Bridge (Tuesday 5 October 2021 to Tuesday 25 October 2022). Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8am and 5pm.

Highway Infrastructure Projects (HIPs):

  • A41 Bicester Road - Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury (Tuesday 1 June 2021 to 30 June 2022). Works will continue on west bound A41 at Stone Bridge to undertake carriageway widening works, construction of new pedestrian island and surfacing. This will be undertaken under 2-way lights between 9.30am and 3.30pm, using a lane closure on the west-bound carriageway.

Intelligent Traffic Signal Schemes:

  • Stoke Road, Aylesbury – Adjacent to the Railway Bridge (Monday 25 April to Thursday 29 April). Comms cabinet upgrade using a footway closure operation Monday to Friday between 9:30am and 3:30pm.