Here is the weekly roadworks update:

Plane and Patch Programme:

Aston Abbotts Road, Aston Abbotts – From Wing Road to High Street (Thursday 28 April to Thursday 12 May)

Surface patching works using a road closure in operation Monday to Friday between 8:00am and 4:00pm.

Surface Dressing Programme:

Smalldean Lane, Saunderton – From A4010 to New Road (Monday 9 May to Friday 13 May)

Surface patching preparation works using a road closure in operation Monday to Friday between 8:30am and 3:00pm.

Drainage Improvement Schemes

West End Lane, Weston Turville – Whole of West End Lane (Monday 19 April to Friday 27 May)

Drainage improvement works using give and take traffic management in operation Monday to Friday between 8:00am and 5:00pm.

Hulcott Lane, Bierton – Hulcott Lane junction with A418 to Cane End Lane junction with A418 (Tuesday 3 May to Friday 3 June)

Drainage improvement works using give and take traffic management in operation Monday to Friday between 8:00am and 5:00pm.

Footway Improvement Schemes

Bellingdon Road, Chesham – From Deansway to Lowndes Avenue (Tuesday 10 May to Friday 3 June)

Footway improvement works using 2-way temporary traffic lights in operation Monday to Friday 9:30am and 3:30pm.

Broadlands Avenue, Chesham – Whole of Broadlands Avenue (Monday 9 May to Monday 6 June)

Footway improvement works using a footway give and take management system in operation Monday to Friday, 8:00am to 5:00pm.

Community Board Schemes

The Lines and Moat Lane, Aston Abbotts – From The Lines to Moat Lane (Monday 9 May to Wednesday 11 May)

Lining improvement works using give and take traffic management system in operation Monday to Friday 9:30 am to 3:30pm.

Wing Road, Cubblington – From High Street crossroads to Cublington village gateway on Wing Road (Monday 9 May to Wednesday 11 May)

Lining improvement works using give and take traffic management system in operation Monday to Friday 9:30am to 3:30pm.

Street Lighting Schemes

Suffield Road, High Wycombe – Outside No. 46, No. 48, No. 49, No. 67 and junction with West End Street (Monday 9 May)

Lamp column replacement works using two-way temporary traffic lights in operation 9:30am to 3:30pm.

Carver Hill Road, High Wycombe – Outside No. 150 (Tuesday 10 May)

Lamp column replacement works using give and take traffic management in operation between 8:00am and 5:00pm.

Bellfield Road, High Wycombe – Outside No. 1 and adjacent to comet (Tuesday 10 May)

Lamp column replacement works using two-way temporary traffic lights and give and take traffic management in operation 8:00am to 5:00pm.

New Road, High Wycombe – Outside No. 6, No. 11, No. 22a, No. 122, No. 128, No. 140, opposite Five Acre Wood and adjacent to Five Acre Wood. (Tuesday 10 May to Friday 13 May)

Lamp column replacement works using two-way temporary traffic lights in operation between 8:00pm and 6:00am.

Amersham Road, High Wycombe – Outside No. 25 and No. 29 (Wednesday 11 May to Thursday 12 May)

Lamp column replacement works using two-way temporary traffic lights in operation between 8:00pm to 6:00am.

Chiltern Avenue, High Wycombe – Outside No. 142 and No. 159 (Friday 13 May)

Lamp column replacement works using give and take as traffic management in operation between 8:00am 5:00pm.

Bookerhill Road, High Wycombe – Adjacent to New Road (Friday 13 May)

Lamp column replacement works using three-way temporary traffic lights in operation between 9:30am and 3:30pm.

Safety Barrier Repairs

Pyebush roundabout, Beaconsfield – Whole roundabout (Thursday 12 May to Friday 13 May)

Safety barrier repair works using a lane closure aa traffic management in operation 8:00pm to 5:00am.

Bridge Schemes:

High Street, Marlow – Marlow Bridge (Tuesday 5 October 2021 to Tuesday 25 October 2022)

Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.

Highway Infrastructure Projects (HIPs):

A41 Bicester Road - Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury (Tuesday 1 June 2021 to 30 June 2022 – week commencing Monday 9 May)

Works will continue on the eastbound A41 on approach to Jackson Road roundabout with narrow lanes whilst construction works for carriageway and footway widening works are being undertaken. Works will also commence on the westbound A41 approach to Jackson Road roundabout with narrow lanes again whilst construction works for carriageway and footway widening works are being undertaken. Works will be undertaken daytime and two-way traffic flow will be maintained at all times.