This is where Buckinghamshire Highways teams will be carrying out roadworks this week.

The dates below are subject to change at short notice, depending on weather, availability of materials and unforeseen circumstances.

 

Conventional Surfacing Works

The Spans, Brill – (Monday 11 March to Friday 22 March): Conventional surfacing works using a 24/7 road closure.

Neptune Road, Swanbourne – (Friday 23 February to Friday 15 March): Conventional surfacing works using a 24/7 road closure.

Waddesdon Hill, Upper Winchendon – (Monday 4 March Friday 22 March): Conventional surfacing works using a 24/7 road closure.

Manor Road & West End Lane, Cheddington (Tuesday 12 March to Friday 15 March): Conventional surfacing works using a road closure. In operation between 9:30am to 3pm.

Station Road, Amersham Phase 2 – (Wednesday 28 February to Wednesday 13 March): Conventional surfacing works continuation using a road closure. In operation between 8pm and 6am.

 

Footways Resurfacing Works

Gold Hill West, Chalfont St Peter – (Monday 12 February to Saturday 16 March): Footway resurfacing works using a footway closure. In operation between 9:30am and 3pm.

Three Households, Chalfont St. Giles – (Monday 19 February to Tuesday 16 April): Footway resurfacing works using a footway closure. In operation between 8am and 5pm.

Church Road, Penn – (Monday 4 March to 12 April): Footway resurfacing works using a footway closure and temporary traffic lights. In operation between 7am and 7pm.

Wexham Street, Stoke Poges (Monday 11 March to Friday 29 March): Footway resurfacing works using a footway closure and multi-way temporary traffic lights. In operation between 7am and 7pm.

 

Micro-Surfacing Preparation Works

Berryfield Road & The Avenue, Princes Risborough (Friday 8 March to Tuesday 12 March): Micro-Surfacing patching works using a road closure. In operation between 8:30am and 5:30pm.

Green Lane, Prestwood (Wednesday 13 March to Friday 15 March): Micro-Surfacing patching works using a road closure. In operation 8:30am and 5:30pm.

 

Street Lighting Works

Various locations – upgrade of LED lanterns.

Various locations – upgrade of illuminated signs and bollards (located on central traffic islands and roundabouts).

Various locations – upgrade of damaged street lighting columns and removal or damaged stumps.

Belisha Beacons – various locations – upgrade, improvement and re-instatement of beacons, lanterns and posts.

School Wig Wag Units – various locations – upgrade of existing flashing units to Bluetooth technology enabled and corrections / reinstatements to advanced warning signs.

 

Drainage Works      

Bois Moor Road, Chesham Bois (Monday 4 March to Tuesday 23 April): Drainage repair works using multi-way temporary traffic lights. In operation between 9:30am and 3:30pm.

Willow Way, Loudwater (Monday 4 March to Friday 15 March): Capital drainage improvement works using multi-way temporary traffic lights. In operation between 9am and 3pm.

Hulcott lane, Hulcott (Monday 11 March to Friday 22 March): Capital drainage improvement works using a road closure. In operation between 9am and 3:30pm.

 

Road Lining

Hughenden Avenue, High Wycombe – (Wednesday 13 March to Thursday 14 March): Repainting road lining using multi-way temporary traffic lights. In operation between 7:30pm and 6am.